Grid connection services

IN THE NEAR FUTURE, ROSSETI KUBAN’S ACTIVITIES ARE AIMED AT PROVIDING QUALITY AND RELIABLE ELECTRICITY SUPPLIES TO EXISTING CONSUMERS, AS WELL AS INCREASING THE AVAILABILITY OF POWER INFRASTRUCTURE AND ELIMINATING POWER GRID CONSTRAINTS FOR THE GRID CONNECTIONS OF NEW CONSUMERS.

IN 2021, THE NUMBER OF VALID GRID CONNECTION AGREEMENTS INCREASED BY 17% TO 18,465. THE DEMAND FOR GRID CONNECTION IS NOT ONLY CONSISTENTLY HIGH, BUT IS ALSO SHOWING PRONOUNCED GROWTH. MINIMUM 30–35 THS APPLICATIONS ON AVERAGE ARE FILED EVERY YEAR.
chepusov

In 2021, there was a 21% (138 MW) increase in connected capacity for consumers, primarily due to the deferred demand factor activated by the easing of COVID-19 restrictive measures. For the second year in a row, the percentage of agreements not performed on time does not exceed 6% of the total number of ongoing agreements (1,016 agreements at the end of 2021). The main reason for violating deadlines is the applicant’s unreadiness to complete the grid connection procedure. In order to solve this problem, the Company is working out the possibility of implementing the measures, which are in the scope of applicant’s responsibility, as an additional service.

Pursuant to Resolutions of the Government of the Russian Federation No. 262 dated 10 March 2020 and No. 639 dated 26 April 2021, the Company carried out a number of organisational and technical measures to re-engineer the grid connection process; those measures ensured prompt and complete meeting the increased demand for such service. In the future, this will reduce the volume of overdue agreements.

In 2021, the average term for grid connection activities was 94 days, and under agreements concluded with small and medium-sized businesses, it did not exceed 66 days, which is significantly lower than the normative terms established for grid organisations by the current legislation. The average term to consider an application and submit an offer did not exceed nine days".

Alexander Chepusov Deputy General Director for Development and Power Grid Connection, Rosseti Kuban, PJSC

The key documents, which regulate the Company’s activities related to grid connection of consumer terminals (power installations) of legal entities and individuals to Rosseti Kuban power grids:

  • Federal Law No. 35-FZ dated 26 March 2003 On the Electric Power Industry
  • Rules for the Grid Connection of Consumer Terminals of Electricity Consumers, Generating Facilities and Grid Facilities Owned by Grid Operators and Other Entities to Power Grids approved by Decree No. 861 of the Government of the Russian Federation dated 27 December 2004
  • Decree of the Government of the Russian Federation On Pricing in the Field of Regulated Prices (Tariffs) in the Electric Power Industry No. 1178 dated 29 December 2011
  • Order of the Federal Antimonopoly Service (FAS of Russia) On Approval of the Guidelines for Determining the Fees for Grid Connection No. 1135/17 dated 29 August 2017

A complete list of regulatory legal documents, detailed information on the implementation of the grid connection procedure in Rosseti Kuban is publicly available on the Company’s website in the To Consumers / Grid Connection section.

For more details on the grid connection, please visit the Company’s website.

GRID CONNECTION SERVICES

Execution of Grid Connection Agreements

In the reporting year, the Company executed 33,795 agreements for the grid connection to PJSC Rosseti Kuban power grids. The total power supplied under the implemented grid connection agreements amounted to 788 MW, which is 135% more than the planned value. Compared to 2020, the amount of connected capacity increased by 21% (138 MW).

33,795 grid connection agreements fulfilled in 2021
788 MW — the total capacity under the agreements fulfilled (+21% year-on-year)
LOAD CAPACITY CONNECTED IN 2021 BY CONSUMER CATEGORY (MW)

Connection categories

Number of grid connection agreements implemented

Agreements

For total power (MW)

Up to 15 kW inclusive, total

31,832

415

Including individuals

27,504

361

15 to 150 kW inclusive

1,591

103

150 to 670 kW

189

46

Not less than 670 kW

128

218

Electricity generation facilities

3

5

TOTAL, EXCLUDING TEMPORARY GRID CONNECTION

33,743

787

Temporary connection

52

2

TOTAL, INCLUDING TEMPORARY GRID CONNECTION

33,795

788

THE STRUCTURE OF THE ROSSETI KUBAN AGREEMENTS IMPLEMENTED BY CAPACITY CONNECTED (MW AND %)
APPLICANTS WHICH HAD THEIR LARGEST AND MOST SIGNIFICANT ENERGY FACILITIES CONNECTED TO THE COMPANY’S POWER GRIDS IN 2021

Applicant

Load capacity connected (MW)

НЭСК-электросети

JSC NESK Elektroseti

75

Новорослесэкспорт

JSC Novoroslesexport

14

Орленок

Federal State Budgetary Institution All-Russian Children’s Centre Orlyonok

6

Славянск ЭКО

LLC Slavyansk ECO

5

In 2021, significant capacities were allocated to meet the electricity demand of housing construction projects; the high rates of those have persisted in the region in recent years. More than 1,900 agreements for a total capacity of 133 MW were fulfilled.

Also, the agricultural sector and the food industry, which require no less power capacity than other sectors, always play a strategic role in the economic structure of southern Russia.

In 2021, the Company fulfilled more than 900 agreements for grid connection of agricultural facilities, with a total capacity of over 42 MW.

LARGEST APARTMENT BUILDINGS CONNECTED IN 2021 (MW)
LARGEST AGRICULTURAL FACILITIES CONNECTED IN 2021LLC Mirny-Adygea is implementing a project to build a 3,000-strong dairy plant for producing goat milk. (MW)

Consumer demand for grid connection in 2021

In 2021, the Company concluded 38,157 agreements for grid connection to Rosseti Kuban power grids for the total capacity of 931 MW with the total value of RUB 4.3 bn, excl. VAT. Since 2019, the demand for grid connection has remained at a persistently high level. On average, about 30–35 ths applications are received per year and at least 30 ths agreements are signed.

Connection categories

Number of grid connection agreements implemented

agreements

for total power (MW)

Up to 15 kW inclusive, total

35,526

471

Including individuals

30,511

406

15 to 150 kW inclusive

2,178

151

150 to 670 kW

208

47

Not less than 670 kW

153

214

Electricity generation facilities

15

45

TOTAL, EXCLUDING TEMPORARY GRID CONNECTION

38,080

927

Temporary connection

77

4

TOTAL, INCLUDING TEMPORARY GRID CONNECTION

38,157

931

STRUCTURE OF PJSC ROSSETI KUBAN’S AGREEMENTS CONCLUDED IN 2021 BY CAPACITY CONNECTED (MW AND %)

Revenues and monetary funds collected

Revenue from grid connection services in the reporting year amounted to RUB 2,348 mn (excl. VAT), which is 101% of the target and 3.2 times higher than in 2020 (RUB 731 mn). In the reporting year, agreements with major customers were fulfilled, including JSC KTK-R (the first stage of activities under the agreement, RUB 729 mn), JSC Novoroslesexport (RUB 361 mn), State Healthcare Institution Research Institute — KKB No. 1 named after Professor Ochapovsky (RUB 238 mn), Orlyonok All-Russian Children’s Centre (RUB 189 mn), LLC Studio Project Design (RUB 103 mn), LLC Kurortny Residential Complex (RUB 47 mn), JSC NESK-Electroseti (RUB 66 mn), LLC SpetsPharm Production (RUB 19 mn).

In 2021, monetary funds for grid connection services were received in the amount of RUB 2,354 mn (incl. VAT), which is 207% more than the planned value and 22% higher than in 2020 (RUB 1,922 mn, incl. VAT).

The over-performance is due to continuous interaction with applicants to fulfil contractual obligations as soon as possible, including through the provision of additional services to them in relation to the implementation of measures provided by the specification and assigned to scope of applicant’s responsibility — that contributes to a reduction in the time required to fulfil agreements. The over-performance for the indicator related to receipt of funds is associated with advance payments under the grid connection agreements.

In 2022, the Company expects to generate revenue from connection services of at least RUB 1.1 bn (excl. VAT). In 2022, a major grid connection facility in terms of revenues is projected to be JSC Caspian Pipeline Consortium — R, for the second phase of the project (with planned revenues of RUB 421 mn, excl. VAT).

GRID CONNECTION SERVICES

Grid Connection of Generating Facilities

Applicant

Generation facility connected

Required capacity for the grid connection of generating units to power the grid, voltage rating

The grid connection agreement date and price (excl. VAT)

Status of the grid connection of the facility as of the end of 2021

PJSC Rosneft

Tuapse Refinery

24 MW, 110 kV

1 April 2010, RUB 56.7 mn

On 21 December 2016, PJSC Rosseti Kuban notified the Applicant of the completion of work provided for by technical specifications and the readiness to the actual connection of the facility according to the legislation in force.

The grid connection deadline is 30 May 2022

LLC ART-TECH

Electric facilities of a land plot for the arrangement of a logistics centre

6.2 MW, 10 kV

29 May 2020, RUB 4.14 mn

The agreement is being implemented. The grid connection deadline is 29 May 2022

LLC LUKOIL — Kubanenergo

Electrical installations of a land plot for the operation of the base power station

2.25 MW,

35 kV

25 February 2021, RUB 1.52 mn

The agreement is being implemented.

The grid connection deadline is 25 February 2023

OJSC Verkhnebakansky Cement Plant

Power station of OJSC Verkhnebakansky Cement Plant

56.41 MW,

6 kV

3 September 2015, RUB 0.09 mn

The agreement is being implemented.

On 18 February 2019, PJSC Rosseti Kuban notified the Applicant of the readiness to the actual connection of the facility following the procedure compliant with the applicable legislation.

Completion of activities by the applicant is expected

OJSC Novoroscement

GPU (gas piston unit) based energy centre with a capacity of 17,600 kW

17.60 MW,

110 kV

4 March 2019, RUB 11.40 mn

The agreement is being implemented.

On 4 March 2019, PJSC Rosseti Kuban notified the Applicant of the readiness to the actual connection of the facility according to the legislation in force. The grid connection deadline is 4 March 2022 Completion of activities by the applicant is expected

LLC LUKOIL-Ecoenergo

Consumer terminals of a small HPP

1.5 MW, 6 kV

1 December 2020, RUB 13.18 mn

The agreement is being implemented.

The grid connection deadline is 1 December 2022